Feuerberg Mountain Resort

Hotel construction, Bodensdorf

At 1769 metres above sea level, the Carinthian 4*S wellness hotel is located in the middle of the Gerlitzer Alp ski and hiking area. Feuerberg Mountain Resort has received numerous awards and is now considered one of the leading wellness resorts in Austria. During the mid-season of 2025, the hotel carried out some renovation work and added the new “Heaven’s Nest” area.

Project information

Use: Hotel building
Location: Bodensdorf, Carinthia
Completion: June 2025
Theurl products used: 237.45m³ CLTPLUS and 139m³ glulam

Project partners

Client: Mountain Resort Feuerberg
Timber construction: Holzbau Pichler
Photos: © Feuerberg Mountain Resort/Michael Stabentheiner

Fast construction with timber

One challenge was certainly the limited construction period, which was restricted to the mid-season from April to June. Excellent coordination between all parties involved was required to ensure that everything ran smoothly. THEURL delivered in the period from 8 April to 22 April 2025:

  • 237.45m³ CLTPLUS in 6 deliveries by lorry
  • 139m³ glulam in 3 deliveries

The extension of the Himmelsnest is an impressive example of the efficiency and speed of timber construction, as two storeys were added to the building within two days. Increasing progress was made on the building from week to week.

Transport with demanding mountain logistics

Another highlight was certainly the challenging and exciting logistics. Using our swap bodies (WABs) with our own steered trailers, we were able to transport the building materials safely and on time to the Gerlitzen Alp – despite the difficult access road.